Synopsis
'SolarReserve Aurora Solar Energy Plant 150 MW South Australia - Project Profile' contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.
The 'SolarReserve Aurora Solar Energy Plant 150 MW South Australia - Project Profile' is part of World Market Intelligence's database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.
Summary
SolarReserve, LLC (SolarReserve) plans to build a solar thermal plant in South Australia, Australia.
The project involves the construction of a 150MW solar thermal power plant. It includes the construction of a substation and an energy storage system to store 1,100MWh for up to eight hours, the installation of solar panels, generators, 10,000 billboard-sized mirrors and transformers, and the laying of transmission lines.
In February 2016, SolarReserve submitted the project plans to the Department of Planning for approvals.
The project will be funded through Clean Energy Innovation Fund (CEIF). The CEIF will be run by the Clean Energy Finance Corporation (CEFC) and the Australian Renewable Energy Agency (ARENA).
In March 2017, Federal Coalition government has decided to fund US$84 for the project.
On August 14, 2017, SolarReserve entered into a long-term generation project agreement (GPA) with the Government of South Australia (GSA) for the project development.
Construction work is expected to commence in 2018 and will be completed in 2020.
Scope
The project involves the construction of a 150MW solar power plant in Port Augusta, Australia.
The US$512 million project includes the following:
1. Construction of a substation
2. Construction of an energy storage system to store 1,100MWh for up to eight hours
3. Installation of solar panels
4. Installation of generators
5. Installation of transformers
6. Installation of 10,000 billboard-sized mirrors
7. Laying of transmission lines