'MoE Island of Krk LNG Terminal Croatia - Project Profile' contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.
The 'MoE Island of Krk LNG Terminal Croatia - Project Profile' is part of World Market Intelligence's database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.
Summary
The Ministry of Economy, Croatia (MoE) is undertaking the construction of the floating LNG terminal on the Island of Krk in Croatia.
The project involves the construction of the floating LNG terminal with a throughput capacity of two billion m3/year. It includes the construction of a tanker jetty to accommodate the LNG carriers, two LNG storage tanks with a total storage capacity of up to 360,000m3, vaporizers and ancillary equipment.
The project also includes the construction of processing units, a control room, a maintenance workshop, and administration buildings, the installation of unloading facilities, low and high-pressure pumping systems and related equipment, and the laying of gas pipelines.
LNG Hrvatska d.o.o. (LNG Croatia) a company formed by the state power board HEP Group and gas transport operator Plinacro d.o.o has been appointed as the associate developer. The project will be financed 50% by EU funds, 25% by the Government of Croatia (GoC) and the remaining 25% by private investors.
In 2007, the conceptual engineering study was prepared and Sofregaz was appointed as the design consultant in 2009.
In March 2010, the project received environmental acceptability from the Croatian Ministry of Environmental Protection.
In December 2010, the project was placed on hold due to falling gas demand in European markets and economic crisis.
Public consultations on environmental impact assessment (EIA) lasted from January 16, 2014, to February 14, 2014.
On April 20, 2014, the Ministry of Environment and Nature Protection approved the project after evaluating the environmental impact assessment (EIA) report.
In March 2015, PricewaterhouseCoopers (PwC) was appointed as consulting engineer.
In March 2015, MoE initiated the process of reviving the project.
In July 2015, the GoC has identified the project as the strategic investment project.
In January 2016, LNG Croatia received the expression of interest from seven investors for the public call for investment. Out of seven, four offers were from industrial investors and remaining from financial investors, whose names were undisclosed.
On June 6, 2016, the GoC gave approvals for the construction of land-based LNG terminal.
On September 2, 2016, public consultation held.
The project plans were revised to construct a floating LNG terminal which obtained approvals from the GoC. Initially, the project was aimed to construct an onshore LNG terminal with higher capacity, later the plans were put on hold and revised due to the decreasing gas demand.
LNG Croatia has issued tenders for consulting services with submission deadline as November 22, 2016, to obtaining necessary permits and approvals.
In November 2016, Ukraine expressed interest in joining as a partner for the project development.
On November 8, 2016, LNG Croatia has applied for co-financing to the European Union (EU) under the CEF-Energy-2016-2 program.
On February 17, 2017, EU's Connecting Europe Facility (CEF) Coordination Committee has granted US$109 million funds.
During Febr