...85% occupancy that was originally projected for the first and second year of operations. While we understand that there continues to be considerable outreach to prospective students marketing the traditional campus experience and new facilities, we believe the leasing of the facilities in the near term will remain challenged. American Public Development (APD), American Campus Communities (ACC), and NSC meet on a regular basis regarding the development and management of the project, with good cooperation between the three. In addition to construction delays, the project's operating budget has also faced delays, given projected revenue short falls, construction delays, and other operational items. We understand that with a current occupancy rate around 40%, due to substantial cuts in operating costs, including insurance costs, the project is not quite at a break-even occupancy level, but close; however, this excludes debt service costs. Absent any direct financial support from an external...