This project financing comprises an about 2.2 gigawatt power portfolio in the following markets: Lakewood: A 224 megawatt (MW) combined cycle facility. Rock Springs 1, 2, 3, and 4: A 744 MW natural gas peaking facility. OPP: A 374 MW simple cycle natural gas peaking facility. Newington: A 630 MW combined cycle facility. EPMA: A 254 MW portfolio of natural gas, oil, and diesel/kerosene peaking facilities. Our new price assumptions are $2.75/kilowatt (kW-month for the forward capacity auction (FCA15), compared to our previously expected $5/kW-month. FCA15 applies to capacity year 2024-2025. The assumption for FCA16 is $3.50/kW-month, escalating at 2% in future years, compared with the previously expected $5.5/kW-month. Our assumptions are higher than cleared price in FCA14, which was